289 MMSCFD Aguada Pichana (Argentina) Hydrocarbon Refrigeration + Dew Point Control Plant

Contract Type

  • Turnkey EPC


Critical requirements

  • A contractor meeting quality, cost and schedule objectives
  • Imperative to get the product to the market ASAP
  • Tight schedule to meet sales delivery commitments
  • Plant handling 10% of Argentina’s total gas production


Project Milestones

  • Ten and a half (10-1/2) months from award to start-up
  • 117 days from arrival of first skid at site to start-up


Key Dates

  • Award: March 1995
  • Completion Start-Up: January 1996


Project Scope

  • Refrigeration hydrocarbon dew point control plant producing 6,160 BPD of stabilized condensate: Inlet receiving facilities, 2,700 HP gas chilling train, 1,400 HP stabilization system, 20 MMBTU/Hr hot oil system, 9.6 MW power generation system, fire water system, Scada, radio & telemetry system, DCS, permanent camp facilities & office infrastructure.


Modules fabricated in 18-24 weeks, and arrived at site on week 32, after ocean freight transportation. Plant start-up and operation in 10.5 months from contract award




| Home | About Propak | Stock Production Equipment | Engineering Services | Offices & Manufacturing Facilities |
| Propak Systems Worldwide | Fabrication | Turnkey Projects | Products & Field Services | Inquiry Spec Sheets |
| Technical Publications | Careers at Propak | Contact Propak |



Copyright © 2000 "Propak Sytems Ltd". All rights reserved.
This web site designed by 'theWORLDco'.